Rohnert Park Road Improvements Update 9/29/17
Published on Sep 29, 2017 12:12

Enhancements to Rohnert Park Expressway -  University District Development: Brookfield Homes

Contractors will continue performing utility and construction improvements on Rohnert Park Expressway between Snyder Lane and Petaluma Hill Road. In addition, please note there will be utility work be conducted at the intersection of Petaluma Hill Road and Rohnert Park Expressway. Temporary traffic control measures will be in place.

The stretch of roadway along Rohnert Park Expressway between Kerry Road and Petaluma Hill Road remains a single lane road in each direction. Next week there is an anticipated lane change at the intersection of Petaluma Hill Road and RPX.

Allow extra time for your travels and make alternate travel arrangements if possible.  

If you have questions or concerns about construction activities, please call the project hotline at (707) 540-9955.


Rohnert Park Road Preventive Maintenance Project
Snyder Lane Rehabilitation Project

The Contractor completed all the preparation work on Snyder Lane, including sidewalk work, wheelchair ramps, various utility lines, etc. Next week they will focus on the pavement. Starting next week, they will start to pulverize Snyder Lane from Keiser Avenue to Moura Lane. That could take all week. Then on Saturday (9/30), they will micro-crack the roadway. The following week of Oct 2nd , the contractor will overlay the road with new asphalt. Snyder Lane will remain open. As much as is practical, we will maintain 2 lanes opened, but there will be times in which one lane traffic operation will be required.

Redwood/Commerce Rehabilitation Project

Crews have completed digging out the roadway and placing the asphalt overlay. This week they have been uncovering utility covers, such as water valves and sewer manholes. Next week the contractor will be sealing the roadway along Redwood Drive by Martin Avenue, followed by surfacing at the end of the week. Work is being moved to a night operation.

Allow extra time for your travels and make alternate travel arrangements if possible.

If you have questions or concerns about construction activities, please call the project hotline at (707) 540-9955.