Rohnert Park Roadway Improvements Update 8/6/18
Published on Aug 3, 2018 16:03
Rohnert Park Road Improvements Update: August 6, 2018
Enhancements to Rohnert Park Expressway - University District Development: Brookfield Homes
Rohnert Park Expressway Construction
Road reconstruction between Snyder Lane to Petaluma Hill Road will continue this week. Follow traffic control signage and flaggers. Proceed with caution. Traffic will be switched between the #1 (fast) and #2 lane (slow lane) at various locations as work commences along the alignment. The intersections will be closed at Jasmine Circle and at Kerry Road. U-turns will be permitted at Redwood Circle / Knight. Detour signs are installed to help with guidance to specific streets.
To expedite construction, the City has modified the work hours to be from 7:00 am to 7:00 pm Monday through Friday. There will always be at least one eastbound lane open during construction. The westbound lanes will not be affected.
Jasmine Circle Residents:
Jasmine Circle left turn in and left turn out is closed at Rohnert Park Expressway. Jasmine Circle residents will enter and exit at Snyder Lane. Jasmine Circle right turn in and right turn out is open at Rohnert Park Expressway.
Oak View Apartment Residents:
If heading eastbound from Snyder Lane, residents will be unable to make a left hand turn into the complex. Residents can either enter on Medical Center Drive or continue eastbound on RPX and make a U turn at Karrington Road.
Sonoma State University / Green Music Center:
The intersection at RPX and Redwood Circle is being reconstructed. The entrance to the Green Music Center and SSU via Rohnert Park Expressway will be closed from Monday 8/6 until Friday 8/17. Detour signs are posted There is no left turns into or out of campus via Rohnert Park Expressway. The Campus can be accessed via Laurel Drive or East Cotati Avenue.
Thank you for your patience. Please obey all traffic control measures, drive safely and cautiously through the construction zone.
Construction work on Keiser Road this Week
Keiser Avenue – East of Kerry Reconstruction
The City of Rohnert Park has contracted with Brookfield Homes to perform the Keiser Avenue Eastern Reconstruction Project. The project consists of installation of a new water main, recycled water main, storm drain and the reconstruction of Keiser Ave from Kerry Road to Petaluma Hill Road. The project will continue through October 2018. Work hours for this project area are between 7:00 AM and 7:00 PM Monday through Friday and 9am to 5pm on Saturdays.
Keiser Ave will be closed to all traffic from east of the Community Gardens to Petaluma Hill Road during construction in this area. Local residents and patrons of the Community Garden can enter and exit their properties on Keiser Ave via Snyder Lane.
Keiser West of Kerry Road – Team Ghilotti is performing work for the City of Rohnert Park on Snyder Lane and Keiser Avenue. This project consists of installation of a new water main on Snyder Lane between Keiser Ave and Crane Creek (North side). Future work will include installation of a new water main and road paving on Keiser Ave from Snyder Lane to Kerry Rd. The project began the week of July 9, 2018 and will continue through to October, 2018. Work for this project area will take place during daytime working hours between 8:00 AM - 6:00 PM.
For this Week:
8/1 thru 8/15 – Water Main to be installed on Keiser Road – activities include trenching, pipe install and heavy equipment, watch for flaggers.
Work for this project area will take place between 8:00 AM - 6:00 PM.
Thank you for your patience. Please obey all traffic control measures, drive safely and cautiously through the construction zone.
|