Rohnert Park Roadway Improvements Update 11/25/19
Published on Nov 22, 2019 15:13
Rohnert Park Road Improvements Update: November 25, 2019
Downtown Infrastructure Project
Next week will be a 3-day work week, no work will take place over the holiday weekend. Utility work will continue on Enterprise Drive from Commerce Boulevard to State Farm Drive, on State Farm Drive from Rohnert Park Expressway to Enterprise Drive. There will be lane closures on Enterprise and State Farm, one lane in each direction will be open.
The Downtown Sewer Line (State Farm and Enterprise Drive only) is commencing on December 2 and estimated to be finished by December 13.
Hunter Drive is now open to traffic in both directions. The bus stops on State Farm and Enterprise are back in service. Work hours are 7 a.m. - 6 p.m.
G and J Rehabilitation Project
G Section Only - On November 26 and 27 the contractor will be lowering iron, then grinding out on December 2, paving asphalt on December 3, then raising iron on December 4-6.
J Section and Bonnie Avenue will be paved on the week of the 16th. Estimated completion before December 25.
This project is funded with SB-1 Gas Taxes.
Rohnert Park Sidewalk and Driveway Improvements
The contractor will be working on demolition of the sidewalks on Southwest Boulevard next week.
Sunrise Park
The park is estimated to be open to the public by the end of December.
Please obey all traffic control measures, drive safely and cautiously through the construction zone. Please share this notice with others.
|