Rohnert Park Road Improvements Update: March 30, 2020
Rohnert Park Sidewalk and Driveway Improvements
No work is scheduled for this week due to the Coronavirus and the safety of our community.
Work is tentatively scheduled to resume next week including completing the trench drain construction on the north half of the driveway at the Northern Fire Station #2 (Country Club Drive at Golf Course Drive).
The asphalt modifications fronting the station are on hold due to the asphalt plants and rock quarries not delivering material at this time.
Please obey all traffic control measures, drive safely and cautiously through the construction zone. Please share this notice with others.
|