Country Club Drive Construction Update – May 7, 2021
Published on May 7, 2021 09:07

Construction teams are currently working on both sides of Country Club Drive. Current activity includes pouring concrete for the pedestrian ramps on the east side of the street. 

Starting next week (week of May 10), crews will be pouring pedestrian ramps on the west side of the street. 

Motorists should expect localized traffic control at the intersections along Country Club Drive.  Throughout next week, please be aware of intermittent lane closures and lane shifts. Motorist, pedestrians, and bicyclists should use extra caution and follow all signage and safety measures.

Starting in the middle of next week and continuing through the following week, work will be taking place on and near the median.

Project-related tree trimming is anticipated to occur during the week of May 22. Construction teams will speak to residents beforehand to notify them of when trimming will occur near their home.

Over the next three weeks, local traffic control measures will be spread out through the project area; this is prior to any major lane closures, which will be announced in advance.

Please note that all schedules are subject to change due to unforeseen circumstances. Construction work hours are from 8 am to 6 pm, Monday through Friday. 

Thank you for your patience and understanding during this important roadway improvement project. For additional information about this project, please visit www.rpcity.org/traffic and select the Country Club Drive project. Specific questions may be directed to [email protected]