Keiser Avenue Project Updates for Week of October 4, 2021
Published on Oct 1, 2021 17:02

Rohnert Park Road Improvements Update for Week of October 4, 2021:

Keiser Avenue Improvements

Upcoming work (all schedules are subject to change due to unforeseen circumstances)

The underground utility testing has been completed, and the installation of curbs, gutters, sidewalks, and ramps is wrapping up this week.

Next week, construction of the aggregate base of the roadway (which supports, strengthens, and provides drainage for the pavement structure will be completed, and installation of the asphalt pavement road surface will take place (several weeks ahead of schedule). Work on the irrigation system and bioswales continues. Bioswales are vegetated low-lying areas that absorb and filter stormwater runoff, removing debris and pollution.

Keiser Avenue only accessible to residents, community garden visitors

During this project, Keiser Avenue between Snyder Lane and Kerry Road will remain closed to through-traffic, and open to residents and community garden visitors only. Access for these motorists is from Snyder Lane only. Residents of the Redwood Apartments have access from Petaluma Hill Road and Kerry Road. Your access will periodically be impacted by the construction activity, so please allow time for the contractor to accommodate your vehicles when you are entering and exiting the area.

As this work continues, residents in the area should expect work crews, equipment, trucks entering and exiting the area, noise, and dust. For your safety, please be aware of construction activity and equipment, and observe all traffic signs and any flagger instructions.

Thank you for your patience and understanding as we work to provide a smoother, safer roadway.