Keiser Avenue Project Updates for Week of November 29, 2021
Published on Nov 24, 2021 14:51

Rohnert Park Road Improvements Update for Week of November 29, 2021:

Keiser Avenue Improvements

Upcoming work (all schedules are subject to change due to unforeseen circumstances)

The striping and signs for Keiser Avenue are going in this week. Next week, installation of the top soil for the bioswales will be completed. Irrigation work is ongoing and will continue through the end of January, 2022 followed by streetlight installation, which is anticipated for mid-February.

Schedule

We now anticipate the reopening of Keiser Avenue to take place by late November/early December, but the remaining work is weather-dependent. We'll update that schedule as progress is made. Once the roadway is reopened there will continue to be periodic traffic control and temporary lane closures as other project-related work takes place. 

Keiser Avenue only accessible to residents, community garden visitors

During this project, Keiser Avenue between Snyder Lane and Kerry Road will remain closed to through-traffic, and open to residents and community garden visitors only. Access for these motorists is from Snyder Lane only. Residents of the Redwood Apartments have access from Petaluma Hill Road and Kerry Road. Your access will periodically be impacted by the construction activity, so please allow time for the contractor to accommodate your vehicles when you are entering and exiting the area.

As this work continues, residents in the area should expect work crews, equipment, trucks entering and exiting the area, noise, and dust. For your safety, please be aware of construction activity and equipment, and observe all traffic signs and any flagger instructions.

Thank you for your patience and understanding as we work to provide a smoother, safer roadway.