Keiser Avenue Project Updates for Week of March 7, 2022
Published on Mar 4, 2022 11:04

Rohnert Park Road Improvements Update for Week of March 7, 2022:

Keiser Avenue Improvements

Upcoming work (all schedules are subject to change due to unforeseen circumstances)

Installation of the streetlights is continuing, and anticipated to be complete by March 11. Once that is complete and signage is fully installed a final review of the site will take place, which is expected to get underway the week of March 14.

Schedule

The reopening of Keiser Avenue is anticipated for late March, 2022, as there was a short delay due to delivery issues with some streetlight components. We will continue to update the timing of the road reopening as progress is made.

Keiser Avenue only accessible to residents, community garden visitors

During this project, Keiser Avenue between Snyder Lane and Kerry Road will remain closed to through-traffic, and open to residents and community garden visitors only. Access for these motorists is from Snyder Lane only. Residents of the Redwood Apartments have access from Petaluma Hill Road and Kerry Road. Your access will periodically be impacted by the construction activity, so please allow time for the contractor to accommodate your vehicles when you are entering and exiting the area.

As this work continues, residents in the area should expect work crews, equipment, trucks entering and exiting the area, noise, and dust. For your safety, please be aware of construction activity and equipment, and observe all traffic signs and any flagger instructions.

Thank you for your patience and understanding as we work to provide a smoother, safer roadway.