Enhancements to Rohnert Park Expressway - University District Development: Brookfield Homes
Contractors will continue performing utility and construction improvements on Rohnert Park Expressway between Snyder Lane and Petaluma Hill Road. In addition, please note there will be utility work be conducted at the intersection of Petaluma Hill Road and Rohnert Park Expressway. Temporary traffic control measures will be in place.
The stretch of roadway along Rohnert Park Expressway between Kerry Road and Petaluma Hill Road remains a single lane road in each direction. Please stay in your designated lane.
Allow extra time for your travels and make alternate travel arrangements if possible.
If you have questions or concerns about construction activities, please call the project hotline at (707) 540-9955.
2017 Road Preventive Maintenance Project
The 2017 Road Preventive Maintenance Project is underway. The City is performing preventive maintenance work on various streets during the next few weeks.
Next week Monday – Friday, August 28- September 1st: you can expect that an overcoat seal will be applied to streets previously slurry sealed. This will be followed by the restriping of all the affected streets.
During these Maintenance activities residents affected will be asked to follow these instructions:
- Your street may be closed unless flaggers are present to control traffic.
- Please park and drive on adjacent streets not posted. Any vehicles parked within the posted areas during the no parking times may be towed at owner's expense per CVC Section 21367 - Failure to Obey Traffic Control and Devices at Construction Site - will be enforced on this project.
- Please avoid driving, bicycle riding, or walking on sealed streets until new surface cures. Under normal weather conditions, your street will be reopened within 3 to 4 hours after seal coats are applied. Only Emergency Vehicles will be allowed through at any time.
- Please do not permit water to run in gutters or on streets during this period. You may want to turn your sprinklers off for those dates.
- Weather conditions or equipment breakdowns may cause schedule changes.
|