Keiser Avenue Reconstruction Phase 2A Project No. 2017-18

The work is described generally as installation of sewer and storm drain in Snyder Lane and Keiser Avenue, including trench paving, from the north side of Hinebaugh Creek in Snyder Lane to approximately 450 feet east of Snyder Lane in Keiser Avenue.
  • Demolition, site clearing/grubbing, rough grading,
  • Structure demolition,
  • Installation of sanitary sewer main in Snyder Lane (starting north of Hinebaugh Creek) and for 450 feet in Keiser Avenue, including trench paving,
  • Installation of storm drain main in Snyder Lane (starting at Circulo Grande) and for 450 feet in Keiser Avenue, including trench paving,
  • New and existing connections of mains and structures,
  • Miscellaneous paving including creek path concrete, trench paving, and miscellaneous signage and striping.

The Contractor must have a valid California contractor's license, a Class A. The Engineer’s estimate for this project is $1,800,000.

A copy of the drawings, specifications, and bid packet must be obtained from the Draft Tech Blueprint, 1544 Terrace Way, Santa Rosa, CA 95404, telephone: (707) 578-9442, upon payment of a nonrefundable fee as specified by Draftech. No bid will be received for consideration unless the bidder has obtained and paid for a copy of the drawings, specifications, and bid packet from Draftech Blueprinting, Inc. and has listed the bidder's full name and mailing address on the planholder's list with Draftech Blueprinting, Inc. as a potential bidder on this project.


Bids Due:
Monday, April 15, 2019, at 2:00 PM
130 Avram Avenue, Rohnert Park, CA 94928



Bid Documents


Bid Results:

Project Contact:

Liane Ware
CIP Manager
Development Services
Direct Line: (707) 588-2235
Main Phone: (707) 588-2232
Fax: (707) 794-9242
Email: LWare@rpcity.org